100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Summary Critical Path Method (Project management) $5.08   Add to cart

Summary

Summary Critical Path Method (Project management)

  • Course
  • Institution
  • Book

Do you want to learn more about the Critical Path Method or Critical Path Analysis in Project Management? These are the perfect summary notes for you to kick-start your project management career. The Critical Path Method (CPM) uses network diagramming to predict the total project duration preventin...

[Show more]

Preview 2 out of 10  pages

  • Unknown
  • August 16, 2020
  • 10
  • 2020/2021
  • Summary
avatar-seller

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller bmncwango. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $5.08. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

87781 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$5.08
  • (0)
  Add to cart